51St Street Storm Sewer Replacement

LOCATION

Edson, Alberta

CONSTRUCTION DURATION

September – October, 2022

About this Project

The Town sponsored the replacement of a collapsed and damaged section of storm piping on 51 Street in Edson, which straddles the east and westbound lanes of the Yellowhead Highway (Hwy 16). Due to year-end financial constraints, Option collaborated with The Town to adjust the project scope and find cost saving alternatives to reduce the project budget by $112,000. A further $24,000 of savings were found during construction to assist the Town and successfully deliver the project under budget.

Construction particulars included

  • Project start up activities; contract execution, submittals (ECO/ESC Plan, TAS, Schedule, Shop Drawings), and procurement
  • Traffic accommodation measures addressing heavy volume traffic on Hwy 16
  • New storm sewer installation of 600mm CL4 (96m), 1500mm manholes (2), 900mm catch basins (3) and connection leads to the existing infrastructure
  • New wheelchair/bike ramps and the restoration of 40m of curb and gutter
  • Restoration of 1300m2 of asphalt
  • Site restoration

CONSTRUCTION TEAM

Johan Kruithof, General Manager  Brad Buffalo, Superintendent

Brandy Braun, Project Manager  Steven Beath, Foreman

LOCATION

Edson, Alberta

CONSTRUCTION DURATION

September – October, 2022

PROJECT BUDGET

$584,000

FINAL PROJECT VALUE

$560,000

CLIENT

Town of Edson

Pat Fisher, 403.230.1401

patf@edson.ca

CONSULTANT

WSP Canada Inc.
Michael Steffler P.Eng., 780.712.5000

michael.steffler@wsp.com

KEY FIRM

Option Excavating Inc.