ACE Water Transmission Main

LOCATION

County of Vermilion River, Alberta

CONSTRUCTION DURATION

March – September 6, 2023

About this Project

This project, sponsored by the Alberta Central East (ACE) Water Corporation, comprised the installation of water transmission line from Paradise Valley to Range Road 24, comprising 17kms of directionally drilled line and associated residential service connections.

Construction particulars included

  • Project start up activities; contract execution, submittals (ECO / ESC Plan, TAS, Schedule, Shop Drawings), and procurement
  • Horizontal directionally drilled HDPE DR11 100mm (17.14kms) with 200mm HDPE DR 9 casing (925m)
  • Service materials; blow-offs (12), gate valves (2) and air releases (16)
  • Pig launching/retrieval stations (2)
  • Waterline commissioning
  • Connection to the existing infrastructure and preparation for a future phase
  • Site restoration (15,000m2)

CONSTRUCTION TEAM

Johan Kruithof, General Manager  Richard Hrupchuk, Superintendent Brandy Braun, Project Manager  Brad Buffalo, Superintendent   Steven Beath, Sr. Foreman

LOCATION

County of Vermilion River, Alberta

CONSTRUCTION DURATION

March – September 6, 2023

$2,978,000

FINAL PROJECT VALUE

$3,035,000

CLIENT

Alberta Central East (ACE) Water Corporation

CONSULTANT

MPE Engineering Ltd.