Calahoo Road Storm Sewer

LOCATION

Spruce Grove, Alberta

CONSTRUCTION DURATION

May, 2024

About this Project

This project, sponsored by the City of Spruce Grove, comprised of a coordinated partial closure of Calahoo Road to address storm water drainage issues in the area by adding needed infrastructure.

 

Construction particulars included

  • Project start up activities; contract execution, submittals and procurement
  • Traffic control measures establishment and management of changes as work progressed
  • Saw cutting and asphalt/roadway removals
  • Installation of 23m of 300mm DR 35 storm sewer pipe with fillcrete
  • Installation of a 1200mm storm manhole
  • A tie into the existing infrastructure
  • Roadway preparation and asphalt restoration
  • Restoration of curb and sidewalk

CONSTRUCTION TEAM

Johan Kruithof, General Manager  Brad Buffalo, Construction Manager Brandy Braun, Project Manager  Albert (Albie) Kavanaugh, Foreman

LOCATION

Spruce Grove, Alberta

CONSTRUCTION DURATION

May, 2024

PROJECT BUDGET

$114,450

FINAL PROJECT VALUE

$114,450

CLIENT

City of Spruce Grove

Trevor Crawford, CET, 780.962.7620

tcrawford@sprucegrove.org

CONSULTANT

N/A

KEY FIRM

Option Excavating Inc.