Lymburn Esso Station Remediation

LOCATION

Edmonton, Alberta

CONSTRUCTION DURATION

September and November, 2022

About this Project

This project was privately negotiated work associated with the decommissioning of a gas services station in Edmonton, Alberta. Construction consisted of two phases to accommodate site and structural works outside of Option’s scope.

During the initial phase of work, it became apparent that further removals would be needed. Option collaborated with the client to address the additional work within the project’s scheduling constraints.

Phase One included

  • TAS establishment
  • Electrical disconnects and degassing of associated lines
  • Removals consisting of the station canopy, service pumps and tanks including sorting of all removals for disposal/recycling

Phase Two included

  • Extra work as requested by the client to address further removals and additional excavation
  • Contaminated material removal
  • Clean fill replacement and backfill

CONSTRUCTION TEAM

Johan Kruithof, General Manager  Brad Buffalo, Superintendent Brandy Braun, Project Manager  Steven Beath, Foreman

LOCATION

Edmonton, Alberta

CONSTRUCTION DURATION

September and November, 2022

PROJECT BUDGET

$135,500

Extra work $24,000

FINAL PROJECT VALUE

$159,500

CLIENT

Shamrock Property Management Ltd.

CONSULTANT

Long Chain Reclaim Ltd. (LCR)
Myles Ethier, 587.377.7654

methier@lcreclaim.com

KEY FIRM

Option Excavating Inc.