Spruce Grove Industrial Park – Deep Utilities

LOCATION

Spruce Grove, Alberta

CONSTRUCTION DURATION

October – November, 2022

About this Project

This project, sponsored by the City of Spruce Grove, comprised the installation of sanitary and water services in preparation for the sale of a block of industrial lots.

Option collaborated with The City to find $84,000 in cost savings for a revised budget to align the project with year-end financial constraints.

Construction particulars included

  • Project start up activities; contract execution, submittals (ECO/ESC Plan, TAS, Schedule, Shop Drawings), and procurement
  • Deep sanitary installation of 300m of 200mm PVE with 25m, case bored and up to 8m deep, 1200mm manholes (4, 22 vm) and the connection to the existing infrastructure
  • Watermain installation of 250mm (195m), TVS/hot taps (2), fire hydrants with leads (2), connection to the existing infrastructure and preparation for a future connection
  • Installation required threading services between two Trans Mountain /Kinder Morgan Pipelines
  • Restoration of curb/gutter and asphalt
  • Site restoration

CONSTRUCTION TEAM

Johan Kruithof, General Manager  Brad Buffalo, Superintendent Brandy Braun, Project Manager  Steven Beath, Foreman

LOCATION

Spruce Grove, Alberta

CONSTRUCTION DURATION

October – November, 2022

PROJECT BUDGET

$697,000

FINAL PROJECT VALUE

$613,000

CLIENT

City of Spruce Grove

Rae-Lynne Spila P.Eng., 780.962.0651

rspila@sprucegrove.org

CONSULTANT

Scheffer Andrew Ltd.
Patrick Hallonquist, P. Eng., 780.732.7800

p.hallonquist@schefferandrew.com

KEY FIRM

Option Excavating Inc.