Spruce Grove Industrial Park – Deep Utilities
LOCATION
Spruce Grove, Alberta
CONSTRUCTION DURATION
October – November, 2022
About this Project
This project, sponsored by the City of Spruce Grove, comprised the installation of sanitary and water services in preparation for the sale of a block of industrial lots.
Option collaborated with The City to find $84,000 in cost savings for a revised budget to align the project with year-end financial constraints.
Construction particulars included
- Project start up activities; contract execution, submittals (ECO/ESC Plan, TAS, Schedule, Shop Drawings), and procurement
- Deep sanitary installation of 300m of 200mm PVE with 25m, case bored and up to 8m deep, 1200mm manholes (4, 22 vm) and the connection to the existing infrastructure
- Watermain installation of 250mm (195m), TVS/hot taps (2), fire hydrants with leads (2), connection to the existing infrastructure and preparation for a future connection
- Installation required threading services between two Trans Mountain /Kinder Morgan Pipelines
- Restoration of curb/gutter and asphalt
- Site restoration
CONSTRUCTION TEAM
Johan Kruithof, General Manager Brad Buffalo, Superintendent Brandy Braun, Project Manager Steven Beath, Foreman
LOCATION
Spruce Grove, Alberta
CONSTRUCTION DURATION
October – November, 2022
PROJECT BUDGET
$697,000
FINAL PROJECT VALUE
$613,000
CLIENT
City of Spruce Grove
Rae-Lynne Spila P.Eng., 780.962.0651
rspila@sprucegrove.org
CONSULTANT
Scheffer Andrew Ltd.
Patrick Hallonquist, P. Eng., 780.732.7800
p.hallonquist@schefferandrew.com
KEY FIRM
Option Excavating Inc.
Let's start your project today
Let's turn your dream project into a reality! With our expertise and passion, we are committed to bringing your ideas to life. Contact us today and let's get started on making your vision a tangible success. Together, we can create something extraordinary.